Condition Assessment of Thermal Powerplants and TG Foundations
- Detailed investigation on the residual life assessment of structures at various thermal power plants were carried out and feasible vibration reduction schemes provided.
- This include the powerplant structures in BHEL – Raichur, NTPC- Talcher, DVC- Mejia Thermal Power Station, NLC and NMDC Bacheli etc.
- Vibration measurements are taken at structures like TG columns, deck slab, crusher house structure and conveyor gallery.
- Compiled handbook of machine foundations
- Conducted several courses for design engineers